Construction Manager Reports and Newsletters
Community Newsletters
Construction Manager at Risk Reports
April 2021 Bid, Rebid & Value Engineering
Where we are:
- Bids received March 23rd
- $5.6 million over the project budget of $92.8 million
- Filed sub-bids $1.1M over budget
- Major overruns: HVAC ($1.6M), electrical ($468k), and miscellaneous metals ($300k)
- Non-filed bids $4.5M over budget
- Major overruns: steel, concrete, drywall, millwork, curtainwall, and landscaping
Significant value management (VM) across many trades is required to bring the project back within budget. The team has developed a VM list that will ensure bids do not come in over budget when the project goes back out to bid. Currently, the priced items total approximately $7.1M.
- Identified significant value engineering items:
- No significant educational impacts – all changes reviewed with the school
- Building will still be fossil fuel free
- Architecture
- Simplify interior finishes without sacrificing acoustical performance; reduce wood trim
- Simplify geometry without affecting room sizes
- Remove residual exterior sunshade/trellis
- Remove canopy at Washington Street entrance
- Simplify exterior window system
- Simplify exterior details and materials without affecting performance
- Simplify project area and breakout space geometry
- Remove balcony at Media Center
- Structure
- Simplify exterior perimeter details
- Lower floor-to-floor heights by 8” at upper floors
- Simplify concrete pours where possible
- HVAC
- Bring scope in line with Ridley without affecting comfort or air changes per hour
- Simplify metering and controls
- Substitute radiant ceiling panels for radiant light shelves
- Simplify diffuser connections at curved classroom walls
- Electrical
- Bring scope in line with Ridley
- Simplify metering and controls
- Remove audiovisual scope from construction documents and purchase through the project’s soft cost FF&E/technology budget
- Landscape
- Simplify materials such as railings and site furniture without affecting playgrounds or longevity
- Reduce size, quantity, and type of boulders
- Simplify concrete finishes
- Reduce density of shrub/perennial plantings
- Remove pergola structure
How we got here:
This project followed a process that included more cost input than is typical. Below are some of the steps taken to ensure cost certainty at bid time:
- Estimates were provided early at 50% DD rather than relying solely on the customary 100% DD estimate
- Additional estimates were conducted at the 100% DD, 60% CD, and 90% CD milestones
- The 60% estimate included a third estimator
- A market study was completed at the end of 2020 to better understand conditions during an uncertain period
- When necessary, value management studies were performed to bring the project back within budget
Potential contributing factors for bids coming in higher than anticipated include:
- The recent inflation spike in the market, which was not evident even 6–8 weeks earlier
- Significant increases in the price of copper, steel, and lumber
- Estimates may not have fully captured more complex aspects of the project design
- VM items reduce customization and improve efficiency in manufacturing and installation
- The bid process included six addenda, which may have complicated pricing
- This will be resolved in the next round of bidding, as JLA will issue a conformed set of documents incorporating all addenda
Next steps:
To achieve the above and maintain a September 2023 school opening, the team will follow the timeline below:
- April 16th – Jonathan Levi Architects (JLA) provided a new set of construction documents
- April 22nd – Documents became available to bidders
- May 13th – Bids are due
- Week of May 24th – Gilbane GMP to be approved by the Building Commission, School Committee, and Select Board
- Mid-June – Gilbane mobilizes and begins construction onsite
