Skip To Main Content

Construction Manager Reports and Newsletters

Construction Manager Reports and Newsletters

Community Newsletters

Newsletter_53122 (PDF)

Construction Manager at Risk Reports

April 2021 Bid, Rebid & Value Engineering

Where we are:

  • Bids received March 23rd
  • $5.6 Million over the project budget of $92.8 Million
  • Filed Sub Bids $1.1M over budget
    • Major overruns: HVAC ($1.6M), Electrical ($468k), and Miscellaneous Metals ($300k)
  • Non-filed Bids $4.5M over budget
    • Major overruns: Steel, concrete, drywall, millwork, curtainwall, and landscaping 

Significant value management (VM) across many trades is required to get the project back within budget. The Team has developed a VM list that that will ensure bids do not come in over budget when the project goes back out to bid. Currently, the priced items total approximately $7.1M. 

  • Identified significant Value Engineering items –
    • no significant educational impacts – all changes reviewed with the School
    • building will still be Fossil Fuel Free 
  • Architecture
    • Simplify interior finishes without sacrificing acoustical performance. Reduce wood trim.
    • Simplify geometry without affecting room sizes
    • Remove residual exterior sunshade / trellis
    • Remove canopy at Washington Street entrance
    • Simplify exterior window system
    • Simplify exterior details and materials without affecting performance
    • Simplify project area and break out space geometry
    • Remove balcony at Media Center 
  • Structure
    • Simplify exterior perimeter details
    • Lower floor to floor heights by 8” at upper floors
    • Simplify concrete pours where possible 
  • HVAC
    • Bring scope in line with Ridley, without affecting comfort or air changes per hour
    • Simplify metering and controls
    • Substitute radiant ceiling panels for radiant light shelves
    • Simplify diffuser connection at curved classroom wall 
  • Electrical
    • Bring scope in line with Ridley
    • Simplify metering and controls
    • Remove Audio Visual scope from construction documents and purchase through the Project’s soft cost FF&E/Technology budget
  • Landscape
    • Simplify materials such as railings and site furniture without affecting playgrounds or longevity
    • Reduce size, quantity, and type of boulders
    • Simplify concrete finishes
    • Reduce density of shrub / perennial plantings
    • Remove pergola structure

How we got here:

It’s important to understand that this project followed a process that received more cost input than is typical. Below are some of the steps the project took to ensure cost certainty at bid time:

  • Estimates were provided early at 50% DD rather than relying solely on the customary 100% DD estimate
  • Additional estimates were conducted at the 100% DD, 60% CD, and 90% CD milestones
  • The 60% estimate included a 3rd estimator
  • A market study was completed at the end of 2020 to better understand where the market was headed in these unprecedented times
  • When necessary along the way, the project preformed VM studies to bring the project back within budget 

Potential contributing factors for bids coming in higher than anticipated include:

  • The major inflation spike that the market is currently going through, which was not obvious even 6-8 weeks ago
    • Significant increases in the price of copper, steel, lumber
  • Even with multiple estimators reviewing the same drawings, the estimates don’t seem to have captured the more challenging aspects of the design of the project
    • VM items decrease customization and create more efficiency for manufacturing parts and during installation
  • The bid process included six addenda, which may have complicated the pricing exercise
    • This issue will be resolved in the next round of bidding as JLA will be issuing a conformed set of documents that include the information issued by addenda in the first round of bidding 

Next steps: 

To achieve the above and maintain a September 2023 school opening, the team will follow the timeline below: 

  • April 16th – Jonathan Levi Architects (JLA) provided a new set of construction documents
  • April 22nd – Documents became available to bidders
  • May 13th – Bids are due
  • Week of May 24th – Gilbane GMP to be approved by Building Commission, School Committee, Select Board
  • Mid-June – Gilbane mobilizes and begins construction onsite