Skip To Main Content

Logo Image

Logo Title

Construction Manager Reports and Newsletters

Community Newsletters

Newsletter_53122 (PDF)

Construction Manager at Risk Reports

April 2021 Bid, Rebid & Value Engineering

Where we are:

  • Bids received March 23rd
  • $5.6 million over the project budget of $92.8 million
  • Filed sub-bids $1.1M over budget
    • Major overruns: HVAC ($1.6M), electrical ($468k), and miscellaneous metals ($300k)
  • Non-filed bids $4.5M over budget
    • Major overruns: steel, concrete, drywall, millwork, curtainwall, and landscaping

Significant value management (VM) across many trades is required to bring the project back within budget. The team has developed a VM list that will ensure bids do not come in over budget when the project goes back out to bid. Currently, the priced items total approximately $7.1M.

  • Identified significant value engineering items:
    • No significant educational impacts – all changes reviewed with the school
    • Building will still be fossil fuel free
  • Architecture
    • Simplify interior finishes without sacrificing acoustical performance; reduce wood trim
    • Simplify geometry without affecting room sizes
    • Remove residual exterior sunshade/trellis
    • Remove canopy at Washington Street entrance
    • Simplify exterior window system
    • Simplify exterior details and materials without affecting performance
    • Simplify project area and breakout space geometry
    • Remove balcony at Media Center
  • Structure
    • Simplify exterior perimeter details
    • Lower floor-to-floor heights by 8” at upper floors
    • Simplify concrete pours where possible
  • HVAC
    • Bring scope in line with Ridley without affecting comfort or air changes per hour
    • Simplify metering and controls
    • Substitute radiant ceiling panels for radiant light shelves
    • Simplify diffuser connections at curved classroom walls
  • Electrical
    • Bring scope in line with Ridley
    • Simplify metering and controls
    • Remove audiovisual scope from construction documents and purchase through the project’s soft cost FF&E/technology budget
  • Landscape
    • Simplify materials such as railings and site furniture without affecting playgrounds or longevity
    • Reduce size, quantity, and type of boulders
    • Simplify concrete finishes
    • Reduce density of shrub/perennial plantings
    • Remove pergola structure

How we got here:

This project followed a process that included more cost input than is typical. Below are some of the steps taken to ensure cost certainty at bid time:

  • Estimates were provided early at 50% DD rather than relying solely on the customary 100% DD estimate
  • Additional estimates were conducted at the 100% DD, 60% CD, and 90% CD milestones
  • The 60% estimate included a third estimator
  • A market study was completed at the end of 2020 to better understand conditions during an uncertain period
  • When necessary, value management studies were performed to bring the project back within budget

Potential contributing factors for bids coming in higher than anticipated include:

  • The recent inflation spike in the market, which was not evident even 6–8 weeks earlier
    • Significant increases in the price of copper, steel, and lumber
  • Estimates may not have fully captured more complex aspects of the project design
    • VM items reduce customization and improve efficiency in manufacturing and installation
  • The bid process included six addenda, which may have complicated pricing
    • This will be resolved in the next round of bidding, as JLA will issue a conformed set of documents incorporating all addenda

Next steps:

To achieve the above and maintain a September 2023 school opening, the team will follow the timeline below:

  • April 16th – Jonathan Levi Architects (JLA) provided a new set of construction documents
  • April 22nd – Documents became available to bidders
  • May 13th – Bids are due
  • Week of May 24th – Gilbane GMP to be approved by the Building Commission, School Committee, and Select Board
  • Mid-June – Gilbane mobilizes and begins construction onsite